Transforming our building

UPDATE:

After-hours work permit variance at the Ford Foundation / 320 East 43rd Street

Most of the major work during the life of the project will be completed during regular construction hours, however, the project schedule will occasionally require work to be completed after regular hours. On Friday March 10, 2017 the construction team will be extending hours, and work will take place continuously from 8:00 AM Friday morning through 8:00 PM Sunday, March 12, 2017. On Monday, March 13, 2017 through Thursday, March 16, 2017 the crew will be using a back-up generator continuously between 3:00 PM and 10:00PM to facilitate the required building shut down. All work will be interior work and not expected to be visible to the outside.

 

43rd Street Exterior Construction Work – Between February 22, 2017 and the end of April 2017: 

  • Construction of scaffolding and a wall of protection to contain work within the existing Porte Cochere / Entrance area
  • Installation of plywood protection and leveling deck over existing brick paved driveway area
  • Temporary removal of the CitiBike parking station between 2/22/17 and 4/3/17
  • Installation of exterior hoist (between 2/22/17 and 4/3/17) 
  • Construction of plywood sidewalk protection / pedestrian walkway East and West of the hoist location
  • Construction of a raised plywood loading dock area adjacent, and leading, to the hoist car locations

Refer to the Site Logistics Plan for duration of time.

 

For fifty years, the Ford Foundation’s headquarters has been a gem of New York architecture and a beacon for the social justice community. In October 2016, we began a major renovation and restoration project that will reinvigorate our building’s mission—ensuring that it works for far more people, is open to the public, and serves as an uplifting and energizing space for change.

The site logistics plan below provides a look at construction activity ahead. Please note that there will be increased trucking activity during construction.

Questions about the renovation? Email: [email protected]

Ford Foundation building site logistics plan Ford Foundation building site logistics plan
Key dates

October 8, 2016  Ford Foundation is completely moved out of the building

October 11, 2016  Building windows are obscured

Early 2017  Construction fencing and sidewalk bridging are in place

When we reopen in 2018, it will be as the Ford Foundation Center for Social Justice. The building will be a contemporary workspace that is collaborative, open, and green. It will feature a welcome center, an art gallery, and two full floors for events and programs—as well as space for like-minded organizations. We look forward to welcoming you then.

In the meantime, learn about our interim office at 1440 Broadway.